ESTIMASI BIAYA DAN WAKTU DALAM PROJECT PLAN PEMBUATAN WEBSITE DENGAN PENDEKATAN INFORMATION TECHONOLOGY (IT) PROJECT MANAGEMENT (Studi Kasus Pada Kecamatan Sebangau Kota Palangka Raya)

DOI:

https://doi.org/10.47111/jti.v8i1.1457

Keywords:

time management, cost management

Abstract

The project is an activity that can be planned and implemented in a unified form using a
range of resources to obtain profit. The project involves two parties work together to comply with
the agreed rules. The failure of a project is very common. This is due to the lack of proper
management of the resources that must be managed. The failure of the project not only resulted in
loss of time, but more fatal is the financial loss. The two parties involved in the project will be
equally menanggun a result of the failure of the project. Subdistrict sebagau of duty and service to
the community and government, planning a website design project. In this plan, the districts
involving a consultant in planning, especially in the estimation of the cost and time required.
This study projecting the need for cost and time views of the need for the scope of work /
projects using Information Technology Project Management approach in the area of Time
Management and Cost Management.
From the research, in building a website District Office Sebangau Palangkaraya takes 8
months with an estimated cost of Rp. 184 565 000, -

Downloads

Download data is not yet available.

References

McNurlin Barbara C. 2006. Information Systems Management In Practice. Prentice Hall, New Jersey.

Siahaan Hinsa. 2007. Manajemen Risiko.Elek Media Komputindo, Jakarta Sudarna Made. 2012. Manajemen Proyek Teknologi Informasi. Udayana University Press, Bali

Schwalbe Kathy, 2011. Managing Information Technology Projects. Course Technology Cengage Learning. Canada

Downloads

Published

2014-01-31